NEW QUESTION # 269
In which case can a Sprint be cancelled?

  • A. The Scrum Master cancels the Sprint.
  • B. All Sprint Backlog items were finished.
  • C. The Sprint Goal becomes obsolete.

Answer: C


NEW QUESTION # 270
Which Scrum Events are formal opportunities for inspecting and adapting?

  • A. Product Backlog Refinement
  • B. Product Backlog Grooming
  • C. Sprint Review
  • D. Sprint Retrospective

Answer: C,D


NEW QUESTION # 271
What can be done to reduct technical debt?

  • A. Improve the Definition of Done.
  • B. Have hardening Sprints.
  • C. Include external QA.

Answer: A


NEW QUESTION # 272
Which answer best describes Scrum?

  • A. Scrum is heavyweight, simple to understand, but difficult to master.
  • B. Scrum is heavyweight, simple to understand and simple to master.
  • C. Scrum is lightweight, simple to understand, but difficult to master.

Answer: C


NEW QUESTION # 273
Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism.

  • A. TRUE
  • B. FALSE

Answer: A


NEW QUESTION # 274
What are the 3 Pillars of Scrum?

  • A. Adaptation
  • B. Inspection
  • C. Transparency
  • D. Creativity
  • E. Openness
  • F. Focus

Answer: A,B,C


NEW QUESTION # 275
Sprint Review is not a formal meeting.

  • A. True
  • B. False

Answer: A


NEW QUESTION # 276
The Scrum Values are: commitment, courage, creativity, openness, and respect.

  • A. False
  • B. True

Answer: A


NEW QUESTION # 277
When n teams are working on the same product, one person can be a member of more than one team of Developers.

  • A. True
  • B. False

Answer: A


NEW QUESTION # 278
When n Scrum teams are working on a product, there are n Sprint Backlogs but only 1 Product Backlog.

  • A. True
  • B. False

Answer: A


NEW QUESTION # 279
What is a typical task for the Developers in Sprint 0?

  • A. Set up the project infrastructure.
  • B. There is no Sprint 0.
  • C. Get to know each other better.

Answer: B


NEW QUESTION # 280
Which of the following actions may a Scrum Master take in starting up a project?

  • A. Ensure that a bonus system is in place for the top performance of individuals.
  • B. Ensure that team members have clear roles and responsibilities.
  • C. Ask the Development Team members to introduce themselves to each other and tell about their skills and background.
  • D. Ask the development managers to introduce their departments and capabilities.

Answer: C


NEW QUESTION # 281
To double the Developers will double the productivity.

  • A. False
  • B. True

Answer: A


NEW QUESTION # 282
Each artifact contains a commitment. For the Product Backlog it is the Product Goal.

  • A. TRUE
  • B. FALSE

Answer: A


NEW QUESTION # 283
Where is an evolving environment reflected in Scrum?

  • A. In the number of Product Owners assigned to the Team.
  • B. In the Scrum Team salary.
  • C. In the Product Backlog.

Answer: C


NEW QUESTION # 284
What can be used by the Product Owner to identify unfinished work at the end of the Sprint.

  • A. The Definition of Ready.
  • B. Ask the Scrum Master.
  • C. The Definition of Done.
  • D. Coding Standards.

Answer: C


NEW QUESTION # 285
During the Sprint, the Sprint Backlog can be modified even if it endangers the Sprint Goal.

  • A. TRUE
  • B. FALSE

Answer: B


NEW QUESTION # 286
What does a burn-down chart measure?

  • A. Budget remaining across time.
  • B. Work remaining across time.
  • C. Work left based on the Definition of Done.

Answer: B


NEW QUESTION # 287
Is it allowed to have other meetings besides the Scrum events?

  • A. YES
  • B. NO

Answer: A


NEW QUESTION # 288
Which topics are not appropriate for the Sprint Retrospective?

  • A. The plan for the next Sprint.
  • B. Presentation of "Done" items from the last Sprint.
  • C. The Definition of Done.
  • D. The collaboration model/details.

Answer: A,B


NEW QUESTION # 289
As a Product Owner, which of the following tasks should you do?

  • A. Coaching the Scrum Team how to use Scrum.
  • B. Decomposing Product Backlog items.
  • C. Creating the Product Backlog items.
  • D. Managing the Product Backlog.

Answer: C,D


NEW QUESTION # 290
It is not allowed that the Product Owner is a Developer (part of the "Developers") at the same time.

  • A. False
  • B. True

Answer: A


NEW QUESTION # 291
Developers in a Scrum Team are responsible for holding each other accountable as professionals.

  • A. TRUE
  • B. FALSE

Answer: A


NEW QUESTION # 292
The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how).

  • A. TRUE
  • B. FALSE

Answer: A


NEW QUESTION # 293
The Developers have an internal conflict with one of the team members .
What should the Product Owner do?

  • A. Remove the Developer from the team?
  • B. Let the team handle the conflict internally - they are self-organizing!
  • C. Ask the Scrum Master to remove the Developer from the Team?

Answer: B


NEW QUESTION # 294
......